The Main Body of China Telecom Zhengzhou Airport Data Center is Topped Out with 6000 racks in the First Phase.

Recently, all the main structure of the first phase of the project of China Telecom Zhengzhou Airlines Port Data Center was topped out.

 


China Telecom Zhengzhou Airport Data Center, also known as China Telecom Central Data Center, is located in Zhengzhou Airport Economic Comprehensive Experimental Zone, Henan Province. It is a large-scale data center fully invested by China Telecom. The available land area for data center construction is 138 mu. The overall plan of the project is to build seven data centers, two oil engine buildings, one substation and one comprehensive service center, with a total construction area of about 180,000 square meters and a total investment of 3.4 billion yuan. The data center is designed to accommodate about 28,000 cabinets, and will focus on optical fiber networks, cloud computing data management centers, IDC data management centers, and large-channel transmission. The construction will be implemented in stages, and the construction will be undertaken by China Construction Seventh Bureau. China Telecom Zhengzhou Airport Data Center Park is a one-time plan and will be constructed in stages, which will be constructed by China Construction Seventh Bureau. According to reports, the data center will focus on optical fiber network, cloud computing data management center, IDC data management center, and large-channel transmission.

 

The first phase of the data center will start on October 23, 2021. The total construction area of the first phase of the project is 43,000 square meters, and the total investment of civil construction is 220 million yuan. The main construction contents include: No. 1 and No. 2 data centers, No. 1 oil engine building and outdoor auxiliary works; the first phase of mechanical and electrical engineering construction racks 5,744, with an average power consumption of 6kw and a total investment of 770 million yuan.

 

At present, 80% of the secondary structure construction of the first phase of the data center project has been completed, and the pipeline network, fire protection, water and electricity construction, etc. are being carried out simultaneously.




About IDCNova

IDCNova (Website: www.idcnova.com) is registered under the Hong Kong based Digital Intelligence International Company Limited. As the international presence of Zhongke Zhidao (Beijing) Co Ltd, Ditital Intelligence International aimes at establishing IDCNOVA as a professional media and consulting organization focusing on Internet data center and cloud computing industry, with proactive participation in global emerging markets.


IDCNOVA shares the parent company's unparalleled industry resources and influences in China to track the growth of the ecosystem by delivering news and professional advise on data center in China.


Research Report


2021-2022 China Data Center Industry Electromechanical Equipment Market Research Report

2021-2022 China Data Center Industry Electromechanical Equipment Market Research Report.pdf


2020-2021 China IDC Market Research Report

Sample 2020-2021 China IDC Market Research Report.pdf


2020-2021 IDC Market Analysis Report in Beijing and Surrounding Areas 

Sample 2020-2021 IDC Market Research Report for Beijing and Surrounding Areas.pdf


2020-2021 IDC Market Analysis Report in Shanghai and Surrounding Areas 

Sample 2020-2021 IDC Market Research Report for Shanghai and Surrounding Areas.pdf


2020-2021 IDC Market Research Report for Guangzhou-Shenzhen and Surrounding Areas

2020-2021 IDC Market Research Report for Guangzhou-Shenzhen and Surrounding Areas.pdf


For industry insights, please contact pm.s@idcnova.com


English Website: www.idcnova.com


Wechat Account: erweima.jpg

Twitter: @idcnova



Read Also
21Vianet Executive Personnel Changes: SHEN Yuanqing Stepped Down as Rotating CEO, and the Group President DONG Jie Took Over
The Main Body of China Telecom Zhengzhou Airport Data Center is Topped Out with 6000 racks in the First Phase.
IDCC2022 Opinion: ZHAO Haifeng from Zhongshishun Technology - Data Center Asset Management Should Adhere to the Concept of "Unattended"

Research