XTX Markets Launches 22.5MW Data Center in Kajaani, Finland, With Second Facility Due in 2027

By: IDCNOVARegion: Europe
Algorithmic trading firm XTX Markets has brought its first data center online in Kajaani, Finland, marking a significant step in the company's effort to bring its compute infrastructure in-house. The facility, which offers 22.5MW of capacity, sits on a 193-hectare site and spans 15,000 square meters (161,460 square feet). A second data center building on the campus is scheduled to become operational in 2027.

The launch represents the first time XTX Markets will run its deep learning workloads — used to analyze large volumes of data and forecast prices for global financial instruments — on compute housed within its own data center infrastructure. Previously, the company leased data center space across Europe, necessitating a major migration effort that included physically transporting compute and storage equipment to Finland without disrupting trading operations. In one six-week period alone, the team moved 417 petabytes of storage capacity.

Mike Irwin, COO of XTX Markets, said the company set an ambitious timetable for its first data center and delivered on it. He noted that the second facility is scheduled for completion in 2027, with more planned, and that XTX has already invested over €400 million ($437.73 million) in construction, overwhelmingly with Finnish companies, with ambitions to invest billions more.

Irwin also raised concerns about government bureaucracy and what he described as a worrying lack of engagement regarding the expropriation process for grid development, noting that permits which once took months can now take years. He said businesses cannot reasonably be expected to commit billions of euros while leaving critical infrastructure decisions in administrative limbo, adding that the issue is not about demanding electricity capacity that does not exist but about the government's ability to process applications, make decisions, and engage with investors who are already delivering substantial economic benefits. He concluded that XTX remains committed to Finland for decades and remains willing to work with government and industry, including contributing financially to infrastructure solutions that benefit Finland more broadly, but that long-term commitments require long-term certainty.

XTX is building a third data center at the campus, with construction slated for completion in 2028, though the company said government expropriation permitting delays mean power availability remains uncertain for that facility. The company has taken steps to limit environmental impact: construction was paused when sand martin nests were discovered, waiting until the nesting period had ended, and surveys using a trained detection dog helped identify potential flying squirrel habitats during the design of underground cable routes, with trees marked for retention and routes adjusted to avoid identified areas. The data center also operates without consuming water for cooling, placing no cooling-related demand on the local water supply. XTX has additionally pledged €1.6 million ($1.75 million) to community initiatives, including community facilities and developing workforce skills and education in the area.

The company's plan for the data center was first revealed at the start of 2025, with YIT serving as the main contractor. XTX and YIT announced plans for and started construction on a second facility later in 2025, and the third was announced in June 2026.