Stockland and EdgeConneX Plan A$5 Billion 365MW AI Data Centre Campus at Kemps Creek, Western Sydney

By: IDCNOVARegion: Oceania
Stockland, one of Australia's largest diversified property groups, has unveiled plans for a A$5 billion data centre campus at Kemps Creek in Western Sydney in a 50/50 joint venture with global data centre operator EdgeConneX, marking a significant expansion of the ASX-listed company's pivot from logistics land into digital infrastructure.

The environmental impact statement (EIS) for the Aldington Road project, which has been open for public comment since November 19, 2026, sets out a maximum IT load of 365MW across two buildings containing 33 data halls on a 30.5-hectare site within the Mamre Road industrial precinct. The campus is designed to serve "AI/Hyperscaler" customers, with halls engineered for both air-cooled and higher-density liquid-cooled computing to support artificial intelligence, cloud computing and other advanced digital workloads. The EIS plans 228 dry air-cooled chillers on the rooftops using a waterless cooling system, achieving a power usage effectiveness of approximately 1.25 before additional acoustic treatment raises the expected figure to 1.36.

Under the plan, power will be drawn directly from Transgrid's 330kV network through a new Ropes Creek switching station that will cut into Line 14, with room for a later connection to Line 30, feeding a 330/33kV substation on site. Of the substation's 1,000MVA capacity, 500MVA is allocated to the data centre, with the remaining half set aside as future capacity for the neighbouring 200 Aldington Road estate. Symphony Infrastructure will deliver the switching station, which will transfer to Transgrid ownership upon commissioning as shared network infrastructure. The EIS states that network modelling has been finalised and provided to Transgrid for review, and the substation is scheduled to be operational by the time the first building is completed.

The project has grown considerably since the NSW Investment Delivery Authority endorsed it on March 27, 2026. Planning department study requirements issued in April covered a campus with total power consumption of up to 245MW, amended requirements by September covered up to 360MW of IT load, and the exhibition notice now lists a maximum power consumption of 444MW. The cost report and greenhouse assessment use 342MW, built up from 15 data halls of 12MW in Building A and 18 of 9MW in Building B. Construction is estimated at 44 months beginning in 2027, at a cost of approximately A$4.99 billion excluding GST, with operations expected to commence in the first quarter of 2029 and reach full load by the first quarter of 2031.

The cost report estimates the build will support about 1,375 full-time equivalent jobs, while approximately 84 staff would run the campus once operational. Stockland says NSW and Australian suppliers, contractors and service providers will receive priority where commercially and technically feasible, and selected NSW apprentices and trainees would be offered placements at operating international data centres. Consultation conducted in August and September reached about 850 nearby addresses through newsletters, online briefings, an information session and doorknocking, with the EIS reporting "general agreement that the Site is a suitable location for a data centre."

The project is one of several Stockland data centre sites at different stages of development. Its Road 1 data centre at Macquarie Park was approved on October 1, its Wetherill Park site is awaiting study requirements from the planning department, and its quarterly update lists about 450MW of secured power across three other pipeline sites: MPark Stage 2, Cherry Lane and Brooklyn. Chief executive Tarun Gupta told shareholders at the annual meeting that the EdgeConneX partnership will "develop, own and operate an Australian portfolio of data centres."

Penrith City Council has requested that the application be referred to the Independent Planning Commission, telling the department in September that the proposed height, then given as 36.4 metres, was "a significant non-compliance" with the 20-metre control; the EIS now specifies a maximum height of 31.5 metres. Public comment closes on December 17, 2026, after which Stockland will respond to submissions before the Minister for Planning and Public Spaces or the Independent Planning Commission determines the application. The project also falls under new NSW regulations for data centres, which include an entry bond of A$30,000 per megawatt, due by December 19, 2026, with final guidelines expected by January 31, 2027.