Search

AWS Details 300MW Data Center Campus at Former Coal Plant in Kozani, Greece

By: IDCNOVARegion: Europe
Amazon Web Services has disclosed plans for a 300MW data center campus in Kozani, northern Greece, through a newly published environmental impact assessment, marking one of the largest digital infrastructure projects in the country and a significant test of repurposing retired coal assets for hyperscale computing.

AWS Details 300MW Data Center Campus at Former Coal Plant in Kozani, Greece
cover-AWS-Details-300MW-Data-Center-Campus-at-Former-Coal-Plant-in-Kozani-Greece
The campus, developed in partnership with Greek state utility Public Power Corporation, will be built at the site of the former Agios Dimitrios coal-fired power plant. According to the assessment reported by OT.gr, the facility will deliver 300MW of power capacity and 240MW of IT capacity across four identical buildings housing 20 data halls, with the potential to scale up to 1GW. The campus will occupy approximately 45 hectares, with the four buildings totaling 77,360 square meters (832,695 square feet) and each reaching 36 meters in height, featuring aluminum composite panel facades and perimeter landscaping.

AWS and PPC intend to reuse some of the infrastructure left behind by the retired coal station, including connecting to the existing 400 kV substations at Agios Dimitrios via two new underground cable lines. The campus will draw on transmission capacity that was once needed by the 1.55GW coal plant, a symbolic transfer of grid infrastructure from fossil fuel generation to digital infrastructure. According to the assessment, between 60 and 90 percent of the cooling load will use water depending on ambient climate conditions, with the remainder relying on air cooling; annual water consumption is estimated at approximately 203,000 cubic meters.

PPC is expected to receive the terms for connecting to the national electricity system soon, and the 300MW agreement is expected to be finalized by the first quarter of 2027. Equipment will then be ordered, with construction hoped to begin in the summer of 2027 and completion targeted by the end of 2028. PPC is investing €1 billion ($1.1 billion) in the project, with AWS contributing a similar amount for the IT infrastructure. AWS holds an option to expand the campus to 1GW and has exclusivity for this capacity until May 2027.

The Agios Dimitrios Power Station, owned by PPC, was the largest of Greece's power plants before being shut down earlier this year. AWS does not yet operate a cloud region in Greece, but launched a Local Zone in Athens in July 2026 and signed four Power Purchase Agreements in the country in November 2024 covering the 44.4MW Vermio wind farms, 35.4MW Mesokorfi, and 29.5MW Koukouras wind farms. The Kozani project underscores a growing trend among hyperscalers of converting former industrial and fossil fuel sites into AI-ready data center campuses, leveraging existing grid connections and brownfield land while pairing new demand with renewable energy procurement.